Aspiring project managers must learn how to perform a variety of tasks in order to get a project started and estimating activity duration is one of them. It’s not always an easy task to estimate the project duration, because doing so needs a Project Manager’s knowledge of some theory, along with the application of some best practices and methodologies.

To estimate activity duration is a lengthy process and it takes time for a long-term project. Ideally, you should involve your core project team in estimating the duration. You should involve the project team, who will work on the project to achieve the project objectives, project management team, and all the identified key stakeholders to make a consensus on the milestone dates, and delivery schedules. Depending on this duration, you can develop a schedule, with milestones for your project.

Estimating activity duration can be for a project phase or product phase and is iterative in nature. It can be changed as work progresses and as new activities identified in your project. Initially, you can estimate your project based on the network diagram (sequencing the activities). It can be further modified based on the changes done in the project during the execution, controlling and monitoring the process.

The PMI® recommends a few project management tools, methodologies, best practices for estimating the duration. They are as follows:

Analogous Estimating

This is a very important methodology that gives you the entire duration estimation. Based on the information on past projects that are similar, you can get a ballpark idea of the entire duration estimation. You may be able to get this information from the Project Management Office or another project manager; you can use this template for your current project. 

Analogous estimating the activity duration is not so accurate in nature; however, it is less costly and less time consuming than other methods. You can frequently use this method when you don’t have sufficient time to do a proper estimate, and you have a deadline. Analogous estimating can be of a part of the project as well since you don’t have to estimate the entire project. You can estimate activity duration for a single phase of the project if the requirement /nature of the phase is very similar to the previous processed project.

Parametric Estimating

This method is more accurate in nature. It is based on a statistical calculation of historical data and other variables. For example, in the design phase in case of a construction project, you may already have the activity duration: cutting 1,000 stones will take 8 hours and so on. If your project is of a similar nature to one performed in the past, it is worth your while to find existing activity duration estimates and historical data from the past project.

Three-Point Estimating

This kind of estimate is based on considering various options like the assignment of the resources, uncertainty, and the risk associated—such as best scenario-based and worst-scenario based. The three-point estimating concept is originated from the PERT (Program Evaluation and Review Technique). Through PERT, we generally estimate three types of duration:

  • Most Likely (M)
  • Optimistic (O)
  • Pessimistic (P)

Of these, Most Likely (M) is based on the resources assigned and Optimistic (O) is based on the best scenario-based analysis. And the last one—Pessimistic (P)—is based on the worst possible scenario-based analysis. Once you have these, you can use some very useful formulas to derive the expected duration. They are as follows:

TE = (O + 4M + P) ÷ 6

Here, TE is expected time, and O, M, P are Optimistic, Most Likely, and Pessimistic duration respectively. In this way, you can understand the importance of PERT in estimating the duration of your project.

Heuristic Estimating

This is also known as Rule of Thumb. You can roughly guess that the entire design phase can take 45% off your entire project time and so on…this is a very useful technique in case of known phases where you can put an imaginary figure based on the experience.

Reserve Analysis

Reserve analysis is a type of contingency reserve. After fixing a schedule for each activity level depending on the activity attributes, you can create contingency reserve timing by adding some percentage in the derived schedule of each activity. It can be changed as work progresses; reducing or increasing depending on the situation.

Conclusion

Estimating the duration of a project—or its various phases—can help you successfully manage a project that comes in on time and on budget. Learn from the lessons your organization has already digested to save yourself time when doing an activity duration estimate. To learn more about successfully managing projects of all types, look to Simplilearn’s online Project Management training courses including PMP Certification.

Our Project Management Courses Duration And Fees

Project Management Courses typically range from a few weeks to several months, with fees varying based on program and institution.

Program NameDurationFees
Professional Certificate Program in Project Management

Cohort Starts: 26 Nov, 2024

10 weeks$ 2,500
PMP® Plus7 weeks$ 1,849
PMP® Renewal Pack Bundle3 weeks$ 649

Get Free Certifications with free video courses

prevNext

Learn from Industry Experts with free Masterclasses

  • The Power of PMP: Learn how a PMP Certification Can Transform Your Career in 2025

    Project Management

    The Power of PMP: Learn how a PMP Certification Can Transform Your Career in 2025

    3rd Dec, Tuesday9:30 PM IST
  • Project Management Career Path: Key Challenges and Pathways in 2024

    Project Management

    Project Management Career Path: Key Challenges and Pathways in 2024

    22nd Oct, Tuesday9:00 PM IST
  • Career Masterclass: Become an AI-Savvy Project Manager: The Skills You Need to Thrive

    Project Management

    Career Masterclass: Become an AI-Savvy Project Manager: The Skills You Need to Thrive

    29th Jul, Monday9:00 PM IST
prevNext