Will you be surprised to see questions related to calculations from the Procurement Management knowledge area in PMP exams? Don’t worry; they are all simple use simple logic. To make it understandable here are some sample questions with details.

Q1: A cost-plus-percentage-cost (CPPC) contract has an estimated cost of $120,000 with an agreed profit of 10% of the costs. The actual cost of the project is $130,000. What is the total reimbursement to the seller?
  1. $143,000
  2. $142,000
  3. $140,000
  4. $132,000
Q2: A cost-plus-incentive-fee (CPIF) contract has an estimated cost of $150,000 with a predetermined fee of $15,000 and a share ratio of 80/20. The actual cost of the project is $130,000. How much profit does the seller make?
  1. $31,000
  2. $19,000
  3. $15,000
  4. none of the above
Q3: A fixed-price-plus-incentive-fee (FPI) contract has a target cost of $130,000, a target profit of $15,000, a target price of $145,000, a ceiling price of $160,000, and a share ratio of 80/20. The actual cost of the project was $150,000. How much profit does the seller make?
  1. $10,000
  2. $15,000
  3. $0
  4. $5,000

Q4: A fixed-price-plus-incentive-fee (FPI) contract has a target cost of $150,000, a target profit of $30,000, a target price of $180,000, a ceiling price of $200,000, and a share ratio of 60/40. The actual cost of the project was $210,000. Calculate the final fee and the final price.

Q5: A fixed-price-plus-incentive-fee (FPI) contract has a target cost of $9,000,000, a target profit of $850,000, a ceiling price of $12,500,000, and a share ratio of 70/30. The actual cost of the project was $8,000,000. Calculate the final fee and the final price.

Q6: A Cost-plus-incentive-fee (CPIF) contract has a estimated cost of $210,000, a fee of $25,000, and a share ratio of 80/20. The actual cost of the project was $200,000. Calculate the final fee and the final price.

Answers

Q1: Estimated Cost= $120,000

Actual Cost= $130,000

Agreed Profit=10%

Reimbursement amount= Actual cost+% profit of actual cost=$130,000+(10% of $130,000)= $143,000

Q2: Estimated Cost= $150,000

Predetermined fee=$15,000

Share Ratio=80/20( 80 is for the Buyer and 20 is for the seller)

Actual Cost= $130,000

Saving = Estimated Cost-Actual cost=$20,000

Profit to seller is Predetermined fee + (Share ratio of seller * Savings) = $15,000+(20%*$20,000)= $19,000

Q3: Target Cost=$130,000

Target Fee=$15,000

Target Price=$145,000

Ceiling Price=$160,000

Share Ratio=80/20( 80 is for the Buyer and 20 is for the seller)

Actual Cost=$150,000

Here, the actual cost is less than the ceiling price and is more than the target cost.

Final Fee=((Target cost-Actual Cost) * Seller ratio) + Target fee=(($130,000-$150,000)*20%+$15,000=(-$20,000*20%)+$15,000= -$4,000+$15,000=$11,000 Final Price=Actual cost + Final Fee=$150,000+$11,000= $161,000. But this is more than the ceiling price which is $160,000. So the final price which the seller gets is $160,000.

So the profit that seller gets is $160,000-$150,000= $10,000

Q4: Target Cost= $150,000

Target Fee=$30,000

Target Price=$180,000

Ceiling Price=$200,000

Share Ratio=60/40(60 is for the Buyer and 40 is for the seller)

Actual Cost=$210,000

Here Actual cost is more than the target price and also higher than the ceiling price. So the seller is in trouble. Let’s see how much he gets?

Final Fee=((Target cost-Actual Cost)*Seller ratio) + Target fee=(($150,000-$210,000)*40%+$30,000=(-$60,000*40%)+$30,000= -$24,000+$30,000=$6,000

Final Price=Actual cost + Final Fee=$210,000+$6,000=$216,000. But this is more than the ceiling price. So the final price is $200,000 J

Q5: Target Cost= $9,000,000

Target Fee=$850,000

Target Price=$9,850,000

Ceiling Price=$12,500,000

Share Ratio=70/30(70 is for the Buyer and 30 is for the seller)

Actual Cost=$8,000,000

Here Actual cost is less than the target price and also lesser than the ceiling price. Let’s see how much seller gets?

Final Fee=((Target cost-Actual Cost)*Seller ratio) + Target fee=(($9,000,000- $8,000,000)*30%+$850,000=($1,000,000*30%)+$850,000= $300,000+$850,000=$1,150,000

Final Price=Actual cost + Final Fee=$8,000,000+$1,150,000=$9,150,000.

Q6: Estimated Cost= $210,000

Predetermined fee=$25,000

Share Ratio=80/20(80 is for the Buyer and 20 is for the seller)

Actual Cost= $200,000

Saving = Estimated Cost-Actual cost = $10,000

Final Fee= (Saving * Seller Ratio) + Predetermined fee=($10,000*20%)+$25,000=$2,000+$25,000= $27,000

Final Price=Actual cos t+ Final Fee=$200,000+$27,000=$227,000

Point of Total Assumption (PTA): This applies to only Fixed price incentive fee contracts and refers to the amount above which the seller bears all the loss of a cost overrun. This happens due to mismanagement. Seller will sometimes monitor their actual cost against the PTA to make sure they are still receiving a profit for completing the project.

Formula is PTA=((Ceiling Price-Target Price)/Buyer’s share ratio) + Target Cost

The PMP training course offered by Simplilearn focuses on key areas that are vital for project management professionals. This comprehensive program covers essential topics, including emerging trends, latest technologies and practices, and core competencies that are necessary for effective project management. The course places a strong emphasis on strategic and business knowledge, underscoring the critical role played by project managers in driving organizational success.

 

Our Project Management Courses Duration And Fees

Project Management Courses typically range from a few weeks to several months, with fees varying based on program and institution.

Program NameDurationFees
Professional Certificate Program in Project Management

Cohort Starts: 16 Nov, 2024

10 weeks$ 2,500
PMP® Plus7 weeks$ 1,849
PMP® Renewal Pack Bundle3 weeks$ 649

Learn from Industry Experts with free Masterclasses

  • How to Successfully Ace the PMP Exam on Your First Attempt in 2024

    Project Management

    How to Successfully Ace the PMP Exam on Your First Attempt in 2024

    5th Mar, Tuesday9:00 PM IST
  • Project Management Career Path: Key Challenges and Pathways in 2024

    Project Management

    Project Management Career Path: Key Challenges and Pathways in 2024

    22nd Oct, Tuesday9:00 PM IST
  • Career Masterclass: Become an AI-Savvy Project Manager: The Skills You Need to Thrive

    Project Management

    Career Masterclass: Become an AI-Savvy Project Manager: The Skills You Need to Thrive

    29th Jul, Monday9:00 PM IST
prevNext